Metra Station Improvement

Metra Construction Alerts

  1. There are no alerts at this time.
Check here for the latest alerts and important project updates
Construction at the new depot building will be resuming Thursday, November 15.  

Comments or concerns regarding the depot construction can be sent using an online form on Metra's website (https://metrarail.com/contact-us) or via telephone at 312-322-6777.

Project Updates

Visit the Metra Depot Construction News Blog for the latest project news, alerts, and updates.

Metra_Before_After

In partnership with Metra, the Village is seeking to improve the existing facilities at the commuter rail station located in downtown Cary.  Metra has assumed the lead role for the construction phase. Metra has already secured a $2 million federal grant that would be used towards the construction of the improvements, with the understanding that costs beyond this grant amount would be covered by the Village. 

 The 2018/2019 improvements at the Metra Station include:

- Fiber optic utility relocation (MCI/Verizon) - COMPLETE

- Fiber Optic Utility Relocation (AT&T) - COMPLETE

- New pedestrian gates/signals at the northwest end of the platform - SCHEDULE TO BE DETERMINED

- New accessible ramp (replacing existing stairs) at the northwest end of the platform - COMPLETE

- New depot building with ticket agent office & secondary shelter along the inbound platform
​  BEGAN 7/9/18; SUMMER 2019 COMPLETION TARGETED 

​- Replacement of the inbound platform structure - SCHEDULE TO BE DETERMINED

Construction of the new station improvements will require temporary pedestrian detours for commuters at certain times. Signage and maps posted on this website will be utilized to help navigate commuters during the construction.